Swansea Free Public Library


CONSTRUCTION UPDATE - SEPTEMBER 20, 2024

  • Footings completed and foundations completed

  • Waterproofing around new foundations complete

  • Masonry for elevator shaft complete

  • Began underground utility work at both the site driveway and the new addition

  • Ongoing compaction of the backfill at the addition

  • New attic insulation installed in existing building

  • Underground plumbing work ongoing in existing building

 

CONSTRUCTION UPDATE - AUGUST 21, 2024

  • Back parking lot area backfilled

  • Footings completed and foundations nearly complete

  • Waterproofing and CMU infill at existing building complete

  • Existing shelving removed to prepare for connection to addition

  • Began geofoam installation at junction of new and existing building

 

CONSTRUCTION UPDATE - JULY 24, 2024

  • Site drainage and septic system installed

  • Continuing to backfill and establish grades in back parking lot area

  • Excavation for footings and foundations completed

  • Compaction testing for footings and foundations completed

  • Footings formed and rebar installed

  • Began pouring footings

 

Construction Update - June 24, 2024

  • The general contractor, Delphi Construction, has mobilized on-site

  • Site fencing and protection was installed

  • A Groundbreaking Ceremony was held on June 1st, 2024

  • Work in the back parking lot began for site drainage and the septic system

  • Abatement was performed in the 1960’s addition to prepare for demolition

  • Additional abatement was performed in the 1890’s portion of the building

  • The 1960’s addition was demolished

  • Site preparation for foundations has begun for the new portion of the building


Groundbreaking Ceremony - June 1, 2024

 

The Swansea Free Public Library broke ground on June 1, 2024! The ceremony took place outside the historic library, with members of the select board, library committee, and library staff members present to commemorate the renovation and expansion project!